diff --git a/site/litepaper.html b/site/litepaper.html index 2e0720097..15c8bbc8e 100644 --- a/site/litepaper.html +++ b/site/litepaper.html @@ -765,6 +765,16 @@ body.all .pager{display:none}

Dates slip. Gates do not. Phase two decides everything. If consumer GPUs cannot prove shards fast enough, Igneum says so and does not launch on promises.

+

The five deliverables of Igneum 2.0

+
+ + + + + +
DeliverableOwnerPass conditionTodayEvidence
D1. A frozen, reproducible baselinethe coordinator with the hash and node lanesan independent operator reproduces the baseline within declared tolerances from the served kit alonePENDING: the kit is pinned by digest (the release manifest); the reference GPU population, the two tests per class and the cost per accepted unit of work are owedigneum-2.0.md
D2. Two architectural experimentsthe class v6 invention lane (a), the multi-family adversary lane (b)the candidate improves against re-optimised adversaries within the preset cost and verification limits, or v6 stands and the experiment is published as a failure(a) TEAM-REPORTED, killed as a class: only the window width reaches the chip; (b) openconnected-state.md
D3. A programmable adversary allowed to survivethe multi-family adversary lane with the k lanethe best supported cost and energy advantage sits inside the chosen competitiveness envelope, with uncertainty publishedMODELLED: the placed and routed core energies served above; the dataset schedule and the state coupling are under evaluationclass-v6-rotating-family.md
D4. A five-year coexistence modelthe research lane with the k lane’s rowsthe model names credible conditions for sustained commodity participation and names where it failsMODELLED, first run served: the DRAM board passes six of seven conditions; the die fails on its machine cost; the thresholds live in the sensitivity workbookcoexistence-model.md
D5. A no-rescue network exercisethe node lane with the build-server lanespecified behaviour with no emergency algorithm change and no privileged interventionPENDING: the prerequisite (proof verification enforced in consensus) is on from block zero on the Igneum 2.0 devnet; the exercise itself is owedfinality-guarantees.md
+

The pins and their pass conditions are docs/plans/igneum-2.0.md; the Today column carries the served labels (TEAM-REPORTED, MODELLED, PROPOSED, PENDING, EXCLUDED) and moves only with a landed document. The acceptance scorecard is the checklist across the twelve gates.

+