Plan cryptanalysis: the floor is DAA 831,600 (a week past publish 2), so the start to quote is 15 October 2026, 09:00 UK, never 14; the payer entity is the project lead's to confirm
The flip comes by signal at the first epoch boundary after a one-day window carries 95 percent (earliest about 00:45 UK on 8 October) or at the floor on 14 October; the week of class v4 hash closes about 00:45 UK on 15 October at the earliest (Friday 16 if the window needs a second day, 21 October if the flip waits for the floor). Section 5.2 and the one page: Igneum Labs LTD (DIFC) as payer is taken from the litepaper and the ledger decisions; its existence, name and standing are confirmed by the project lead before any email goes. Co-Authored-By: Claude Fable 5.1 <noreply@anthropic.com>
This commit is contained in:
parent
69901de402
commit
0df53dc0a9
1 changed files with 9 additions and 9 deletions
|
|
@ -11,9 +11,9 @@ What this plan builds on, read in full: the mixer brief of `docs/plans/funding.m
|
|||
| What is bought | Two paid, independent attacks on the hash class that ships (class v4, generator 4), plus one paper chip-design estimate from an ASIC house, against a frozen target and the published chip model. Not a new puzzle (lane 8 owns that), not the finality rule, not the proof system |
|
||||
| Who | Lot A: one firm with person-days for the structural attacks (the mixer, the chained cache, the shadow block, the acceptance rule, the verifier bound). Lot B: one academic group for the models (time-memory trade-off, the draw census, the era draw, the ladder). Lot C: one ASIC estimation house for k, area, NRE and unit cost at N5 and 28 nm. Shortlist in section 2; nobody has been contacted |
|
||||
| Shape | Three fixed-price lots, each with a stated person-day bound and a timebox; a report published whole, pass or fail, in the ledger, with its fix beside every finding. A cryptanalysis prize is a separate question for the project lead (section 3.3): the NO bounty rule of 6 October 17:35 UTC is a NO DEVICE bounty rule by its text, and the same outcome left "one cryptanalysis prize of USD 50,000 ... escrowed before it is named" as the project lead's call later |
|
||||
| When | 0.3.15's publish 2 landed at 00:43 UK on 7 October 2026; class v4 flips at the floor (about 04:45 UK on 7 October) or by signal inside the one-day window (by about 00:45 UK on 8 October). Seven days of real class v4 hash end seven days after the flip hour. The freeze commit is tagged the morning the week closes; the earliest engagement start is Wednesday 14 October 2026, 09:00 UK if the flip was at the floor, Thursday 15 October 2026, 09:00 UK otherwise, and 15 October is the date to quote until the flip hour is read from the chain (section 4). Firms set their own calendars: the RandomX reviews ran 3 to 6 weeks each and about 9 weeks from commission to the last report |
|
||||
| When | 0.3.15's publish 2 landed at 00:43 UK on 7 October 2026 with the floor at DAA 831,600, a week past the publish. Class v4 flips by miner signal at the first epoch boundary after a one-day window carries 95 percent (earliest about 00:45 UK on 8 October), or at the floor on 14 October. Seven days of real class v4 hash end seven days after the flip hour: about 00:45 UK on 15 October at the earliest. The freeze commit is tagged the morning the week closes; the earliest engagement start is Thursday 15 October 2026, 09:00 UK (Friday 16 October if the window needs a second day; a week later if the flip waits for the floor), never 14 October (section 4). Firms set their own calendars: the RandomX reviews ran 3 to 6 weeks each and about 9 weeks from commission to the last report |
|
||||
| Budget | Low USD 80,000 (Lot A short, Lot B timeboxed, Lot C as a 10-day estimate), base USD 120,000, high USD 160,000 (Lot A at 40 person-days, Lot B at 30, Lot C with a synthesised core at two nodes). Section 5 prices each lot from the public precedents. The whole engagement is one to two weeks of year-1 miner emission at the low price input (`funding.md` B8) |
|
||||
| What the project lead does | (1) approve or amend the scope (section 1); (2) tick the contacts he permits, in order (section 2); (3) decide the prize question (section 3.3); (4) approve the outreach email (section 6) and the sending address; (5) confirm the budget point (section 5). Nothing moves without each |
|
||||
| What the project lead does | (1) approve or amend the scope (section 1); (2) tick the contacts he permits, in order (section 2); (3) decide the prize question (section 3.3); (4) approve the outreach email (section 6) and the sending address; (5) confirm the budget point (section 5); (6) confirm the payer entity, its exact name and standing (section 5.2), before any email goes. Nothing moves without each |
|
||||
|
||||
## 1. Scope
|
||||
|
||||
|
|
@ -157,15 +157,15 @@ Everything, by the standing rules: a paid review is published whole, pass or fai
|
|||
|
||||
### 4.1 The week of real hash
|
||||
|
||||
The clock starts at the class v4 flip, not at the publish. 0.3.15's publish 1 (binaries on the thirteen-field object) ran on the evening of 6 October; publish 2 (the sixteen-field object with `program_class_v4_activation_daa` = the floor, publish DAA + 14,400 rounded up to the epoch, at least 10,800 ahead, and `program_class_v4_signal_window_daa` = 86,400) landed at 00:43 UK on 7 October 2026 (the coordinator's line). The class flips at the first epoch boundary after 95 percent of blue blocks in the window signal, or at the floor regardless (`release-0.3.15.md` section 2; `counter-asic-3-status.md` P2). At about one block a second the floor is about 4 hours after the publish and the full window is 24 hours, so the flip lands between about 04:45 UK on 7 October and about 00:45 UK on 8 October.
|
||||
The clock starts at the class v4 flip, not at the publish. 0.3.15's publish 1 (binaries on the thirteen-field object) ran on the evening of 6 October; publish 2 (the sixteen-field object with `program_class_v4_activation_daa` = the floor and `program_class_v4_signal_window_daa` = 86,400) landed at 00:43 UK on 7 October 2026 with the floor at DAA 831,600, a week past the publish (the coordinator's line, 7 October; the plan's earlier publish + 14,400 figure from `release-0.3.15.md` section 2 was the pre-cut text). The class flips by miner signal at the first epoch boundary after a one-day window carries 95 percent of blue blocks, or at the floor regardless (`counter-asic-3-status.md` P2). So the earliest flip is about 00:45 UK on 8 October (the first full window), a day later for each day the window falls short, and the floor is 14 October.
|
||||
|
||||
| Flip case | The flip | A week of class v4 hash closes | Earliest engagement start |
|
||||
|---|---|---|---|
|
||||
| At the floor (the whole fleet signalling or nobody signalling): about 7 October 2026, 04:45 to 06:00 UK | 7 October, early morning | 14 October 2026, 04:45 to 06:00 UK | Wednesday 14 October 2026, 09:00 UK |
|
||||
| By signal later in the window | 7 October, daytime or evening | 14 October, the same clock hour | Thursday 15 October 2026, 09:00 UK |
|
||||
| At the end of the window | up to 8 October, about 00:45 UK | 15 October, about 00:45 UK | Thursday 15 October 2026, 09:00 UK |
|
||||
| By signal at the first full window | 8 October 2026, about 00:45 UK | 15 October 2026, about 00:45 UK | Thursday 15 October 2026, 09:00 UK |
|
||||
| By signal a day later (the window needs a second day) | 9 October, about 00:45 UK | 16 October, about 00:45 UK | Friday 16 October 2026, 09:00 UK |
|
||||
| At the floor, DAA 831,600 | 14 October | 21 October | Wednesday 21 October 2026, 09:00 UK |
|
||||
|
||||
So the earliest start is Wednesday 14 October 2026, 09:00 UK, and Thursday 15 October 2026, 09:00 UK is the date to quote to a firm until the flip hour is read from the chain.
|
||||
So the start to quote to a firm is Thursday 15 October 2026, 09:00 UK, never 14 October; main moves it a day per day of window shortfall once the flip hour is read from the chain.
|
||||
|
||||
The flip hour is read from the chain (the first block with the v4 program id; `igneum_getRecentBlocks` in 0.3.16, the observer's class column until then), never from a report. Main checks it before this table is quoted to the project lead.
|
||||
|
||||
|
|
@ -191,7 +191,7 @@ Owed before the freeze and not a precondition of it: the O-1.14 laptop run (2 ho
|
|||
|
||||
### 4.3 The calendar after the start
|
||||
|
||||
Firm calendars are theirs. From the RandomX pattern (CCS funded in May 2019; X41 ran 3 to 28 June; Trail of Bits reported 2 July; Kudelski 2 July; Quarkslab 30 July): about 10 weeks from commission to the last report. Outreach, quotes and contracts come before the start and take the firms' time, not ours: a contact the project lead ticks tonight can have a quote back in about a week, so the first contacts should go the week of 7 October if a start near 15 October is wanted; a firm's own backlog decides the real kickoff, and the RandomX round shows one to two weeks between a signed scope and the first engineer-day. The go checklist row (`testnet-go.md`, 9a per `funding.md` B8): the reports in hand before the last announced reset of testnet-1, so the vectors the testnet freezes are the reviewed ones; mainnet never opens without the published reports.
|
||||
Firm calendars are theirs. From the RandomX pattern (CCS funded in May 2019; X41 ran 3 to 28 June; Trail of Bits reported 2 July; Kudelski 2 July; Quarkslab 30 July): about 10 weeks from commission to the last report. Outreach, quotes and contracts come before the start and take the firms' time, not ours: a contact the project lead ticks tonight can have a quote back in about a week, so the first contacts should go the week of 7 October if a start on 15 October is wanted; a firm's own backlog decides the real kickoff, and the RandomX round shows one to two weeks between a signed scope and the first engineer-day. The go checklist row (`testnet-go.md`, 9a per `funding.md` B8): the reports in hand before the last announced reset of testnet-1, so the vectors the testnet freezes are the reviewed ones; mainnet never opens without the published reports.
|
||||
|
||||
## 5. Budget
|
||||
|
||||
|
|
@ -225,7 +225,7 @@ What the precedents say about rates: in 2019 a European firm cost USD 1,400 to 1
|
|||
| C, the ASIC house | 6 to 8 engineer-days: a paper estimate from published cell libraries and the reads-in-flight model, k with a range at one node: USD 12,000 (approximate) | 12 engineer-days: one synthesised lane and the 32-lane shuffle crossbar at 28 nm on an open PDK, N5 by published scaling, NRE and unit cost at two volumes, the FPGA row: USD 25,000 | 20 engineer-days: the above plus a placed-and-routed lane with power from a gate-level simulation of three real class v4 programs, the controller's power from a vendor datasheet, the model-input verdict table in full: USD 35,000 |
|
||||
| Total | USD 80,000 | USD 120,000 | USD 160,000 |
|
||||
|
||||
Inside each point and not extra: the one-week re-run after a parameter move (priced into each fixed sum), the day-rate judging of any finding, the publication. Outside every point: the optional USD 50,000 prize (escrowed separately, only if the project lead says yes), the F2 FPGA hour (USD 2 to 8), the O-1.14 laptop run (agent hours). Against `funding.md` section 2 the line keeps its USD 80,000 to 160,000 row; the review-and-audit bucket stays USD 290,000 to 570,000 with it; all approximate, and the coordinator re-totals when the point is chosen.
|
||||
Inside each point and not extra: the one-week re-run after a parameter move (priced into each fixed sum), the day-rate judging of any finding, the publication. Outside every point: the optional USD 50,000 prize (escrowed separately, only if the project lead says yes), the F2 FPGA hour (USD 2 to 8), the O-1.14 laptop run (agent hours). The payer named throughout this plan and in the email, Igneum Labs LTD (DIFC), is taken from `site/litepaper.html` and `ledger-decisions.md`; the company's existence, exact name and standing as the contracting party are the project lead's to confirm before any email goes, not the plan's to assert. Against `funding.md` section 2 the line keeps its USD 80,000 to 160,000 row; the review-and-audit bucket stays USD 290,000 to 570,000 with it; all approximate, and the coordinator re-totals when the point is chosen.
|
||||
|
||||
Which point this lane recommends: base. Low drops the ladder's law and the uniformity censuses, which are the two questions nothing in the project has measured, and buys a Lot C figure with no synthesis behind it, which is the one number the whole chip model turns on. High buys mostly calendar and a US firm's name. the project lead decides.
|
||||
|
||||
|
|
|
|||